Boulevard Fence Replacement Project Phase 1 – Update

The fence work in Section 11 is complete. Grading in Section 11 is scheduled for next week. Comcast has been notified that they can begin burying their cable on the west side of Winston Ranch.

Masonry work has been completed in Section 12. Crews will be working on cleaning and washing the fencing next week. Removal of the temporary fence and tie-backs to the wood fencing is complete. Demobilization and grading of the area will begin this coming week.

The District greatly appreciates the community’s patience during construction of the new walls. Please contact us through the District website at http://www.fbmud146.org/contact/ with questions or concerns.

Boulevard Fence Replacement Project Phase 2 – Update

Demolition of the leaning stone columns is complete and construction of the new columns will begin next week. Once the new columns are in place, the brick fencing will be tied back into the columns.

The traffic concerns have been addressed and traffic flow and safety should now reflect that.

The contractor reports that the “Closed Sidewalk” barriers are being moved and people are walking around and past them. These barriers are put up by the contractor for your safety. Please respect the work area and don’t move or ignore closed sidewalk barriers.

The District greatly appreciates the community’s patience during construction of the new walls. Please contact us through the District website at http://www.fbmud146.org/contact/ with questions or concerns.