Boulevard Fence Replacement Project Phase 1 – Update

AT&T and Comcast believe service has been restored to all residences in the area. If you are still having issues, please contact AT&T or Comcast to let them know. Otherwise, they will assume everything is good.

The contractor is continuing borings in Section 11 to complete pouring of piers in that area. They will start building wall again the week of October 7. Once Section 11 is completed, the contractor will move back into Section 12 and complete the final fencing of Phase 1.

The District greatly appreciates the community’s patience during construction of the new walls. Please contact us through the District website at http://www.fbmud146.org/contact/ with questions or concerns.