Boulevard Fence Replacement Project Phase 1 – Update

The masonry work in Section 11 is complete. Cleaning and washing of the new fence will continue into next week. Removal of the temporary fence and tie-back of the wood fences to the masonry fence is finished. The fence crews will be demobilizing and grading Section 11 next week. Comcast is being notified that they can begin burying their cable on the west side of Winston Ranch beginning on Oct. 24.

Concrete pouring for the piers in Section 12 will be complete today. The mason has moved back to Section 12 this week and has projected completion (weather permitting) by Nov 1.

There is a small 12 ft. section of fencing along Long Meadow Farms west of Winston Ranch that was overlooked. That small section is being addressed and should be completed soon.

The District greatly appreciates the community’s patience during construction of the new walls. Please contact us through the District website at http://www.fbmud146.org/contact with questions or concerns.